ITAC Assessment: CO0274
ITAC logo
ITAC Assessment: CO0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Metal Products
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 80,000
ft2
Annual Production 1,500,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $109,882 1,791,911
kWh
Natural Gas $3,273 740
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,020

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3137: Use power during off-peak periods $940 $100 - - $940
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,830 $1,490 $1,830
29,894
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,160 $2,960 $1,160
18,757
kWh
- -
04 2.7261: Install timers and/or thermostats $530 $1,200 - $530
-
MMBtu
-
05 2.4133: Use most efficient type of electric motors $3,730 $8,540 $3,730
60,961
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $250 $200 $250
4,103
kWh
- -
07 2.6231: Utilize controls to operate equipment only when needed $400 $900 $400
6,448
kWh
- -
TOTAL RECOMMENDED $8,840 $15,390 $7,370
120,163
kWh
$530
-
MMBtu
$940
TOTAL IMPLEMENTED $3,020 $1,790 $2,080
33,997
kWh
- $940
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs