| Assessment Year | 1991 |
|---|---|
| Principal Product | MASS FLOW METERS |
| NAICS |
n/a
|
| SIC | 3824: Totalizing Fluid Meters and Counting Devices |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
n/a
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 5,344
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $264,867 | 4,294,256 |
kWh
|
$0.062 |
| Natural Gas | $17,760 | 4,695 |
MMBtu
|
$3.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,108 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,056 | - |
$3,342
54,220
kWh
|
- | $(-1,286.0) | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $633 | $1,200 |
$633
10,258
kWh
|
- | - | |
| 03 | 2.6232: Install set-back timers | $516 | $1,200 |
$516
8,499
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $380 | $150 |
$380
6,155
kWh
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $438 | $810 | - |
$438
-
MMBtu
|
- | |
| 06 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $1,428 | $600 |
$381
14,654
kWh
|
$1,047
-
MMBtu
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $2,100 | $4,600 |
$950
36,635
kWh
|
$1,150
-
MMBtu
|
- | |
| 08 | 2.1123: Install automatic stack damper | $340 | $600 | - |
$340
-
MMBtu
|
- | |
| 09 | 2.4133: Use most efficient type of electric motors | $217 | $487 |
$217
3,517
kWh
|
- | - | |
| TOTAL RECOMMENDED | $8,108 | $9,647 |
$6,419
133,938
kWh
|
$2,975
-
MMBtu
|
$(-1,286.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs