ITAC Assessment: CO0131
ITAC logo
ITAC Assessment: CO0131
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product PUMPS & PUMP COMPONENTS
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area
n/a
Annual Production 2,400,000
lb
Production Hrs. Annual 2,210
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $286,263 3,849,062
kWh
Natural Gas $21,736 5,538
MMBtu
LPG $45,000 9,160
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,618 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,979

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4239: Eliminate or reduce compressed air usage $4,946 $8,000 $4,946
66,530
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $984 $250 $984
13,189
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $874 $300 $874
18,171
kWh
- -
04 2.8121: Apply for tax-free status for energy purchases $632 $250 - $632
-
MMBtu
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,639 $1,600 $5,639
-
kWh
- -
06 2.7261: Install timers and/or thermostats $1,035 $150 $939
12,603
kWh
$96
-
MMBtu
-
07 2.2628: Utilize a less expensive cooling method $16,979 $4,000 $769
10,258
kWh
- $16,210
08 2.2511: Insulate bare equipment $1,028 $1,100 $1,028
13,775
kWh
- -
09 2.2514: Cover open tanks $1,934 $1,500 $1,934
71,219
kWh
- -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $589 - $589
7,913
kWh
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $283 $337 $283
3,810
kWh
- -
12 2.6232: Install set-back timers $2,695 $490 $2,695
36,342
kWh
- -
TOTAL RECOMMENDED $37,618 $17,977 $20,680
253,810
kWh
$728
-
MMBtu
$16,210
TOTAL IMPLEMENTED $31,979 $16,377 $15,041
253,810
kWh
$728
-
MMBtu
$16,210
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs