ITAC Assessment: CO0134
ITAC logo
ITAC Assessment: CO0134
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product NEWSPAPERS
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 7,000,000
pieces
Production Hrs. Annual 4,472
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,408 1,211,020
kWh
Natural Gas $8,096 1,908
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,690

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $211 $200 $211
5,275
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $790 $1,162 $790
20,223
kWh
-
03 2.7226: Use computer programs to optimize hvac performance $455 $421 $174
4,396
kWh
$281
-
MMBtu
04 2.6232: Install set-back timers $779 $800 $396
10,258
kWh
$383
-
MMBtu
05 2.1123: Install automatic stack damper $167 $300 - $167
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $445 $674 $445
11,430
kWh
-
TOTAL RECOMMENDED $2,847 $3,557 $2,016
51,582
kWh
$831
-
MMBtu
TOTAL IMPLEMENTED $1,690 $2,257 $1,409
36,049
kWh
$281
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs