Assessment Year | 2014 |
---|---|
Principal Product | Malted Barley |
NAICS | 311213: Malt Manufacturing |
SIC | 2083: Malt |
Sales Range | $50 M to 100M |
# of Employees | 105 |
Plant Area |
75,000
ft2
|
Annual Production | 132,000
ton
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Washington |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $949,062 | 20,238,230 |
kWh
|
$0.047 |
Electricity Demand | $240,683 | 40,519 |
kW-mo/yr
|
$5.94 |
Electricity Fees | $36,001 | - |
|
- |
Natural Gas | $2,056,903 | 380,908 |
MMBtu
|
$5.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $657,757 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $619,894 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.5121: Redesign flow to minimize mass transfer length | $37,907 | $21,000 |
$32,256
694,434
kWh
|
$5,651
-
kW-mo/yr
|
- | - | |
02 | 2.2443: Re-use or recycle hot or cold process exhaust air | $37,863 | $38,930 | - | - |
$37,863
-
MMBtu
|
- | |
03 | 3.4115: Recover and reuse cooling water | $58,681 | $3,764 |
$49,934
1,075,012
kWh
|
$8,747
-
kW-mo/yr
|
- | - | |
04 | 2.1224: Replace boiler | $523,306 | $3,403,664 | - | - |
$233,306
-
MMBtu
|
$290,000 | |
TOTAL RECOMMENDED | $657,757 | $3,467,358 |
$82,190
1,769,446
kWh
|
$14,398
-
kW-mo/yr
|
$271,169
-
MMBtu
|
$290,000 | ||
TOTAL IMPLEMENTED | $619,894 | $3,428,428 |
$82,190
1,769,446
kWh
|
$14,398
-
kW-mo/yr
|
$233,306
-
MMBtu
|
$290,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs