ITAC Assessment: OR0629
ITAC logo
ITAC Assessment: OR0629
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Malted Barley
NAICS 311213: Malt Manufacturing
SIC 2083: Malt
Sales Range $50
M
to 100
M
# of Employees 105
Plant Area 75,000
ft2
Annual Production 132,000
ton
Production Hrs. Annual 7,488
hrs
Location (State) Washington
View Case Study

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $949,062 20,238,230
kWh
Electricity Demand $240,683 40,519
kW-mo/yr
Electricity Fees $36,001 -
Natural Gas $2,056,903 380,908
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $657,757 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $619,894

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.5121: Redesign flow to minimize mass transfer length $37,907 $21,000 $32,256
694,434
kWh
$5,651
-
kW-mo/yr
- -
02 2.2443: Re-use or recycle hot or cold process exhaust air $37,863 $38,930 - - $37,863
-
MMBtu
-
03 3.4115: Recover and reuse cooling water $58,681 $3,764 $49,934
1,075,012
kWh
$8,747
-
kW-mo/yr
- -
04 2.1224: Replace boiler $523,306 $3,403,664 - - $233,306
-
MMBtu
$290,000
TOTAL RECOMMENDED $657,757 $3,467,358 $82,190
1,769,446
kWh
$14,398
-
kW-mo/yr
$271,169
-
MMBtu
$290,000
TOTAL IMPLEMENTED $619,894 $3,428,428 $82,190
1,769,446
kWh
$14,398
-
kW-mo/yr
$233,306
-
MMBtu
$290,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs