| Assessment Year | 1999 |
|---|---|
| Principal Product | Expanded Polystyrene |
| NAICS |
n/a
|
| SIC | 3086: Plastics Foam Products |
| Sales Range | $1 M to 5M |
| # of Employees | 45 |
| Plant Area |
55,000
ft2
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,267 | 1,421,454 |
kWh
|
$0.023 |
| Electricity Demand | $51,619 | 3,228 |
kW-mo/yr
|
$15.99 |
| Electricity Fees | $781 | - |
|
- |
| Natural Gas | $55,547 | 16,611 |
MMBtu
|
$3.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,598 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,367 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $7,848 | - | - | - | - | $7,848 | - | - | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $2,098 | $3,500 |
$890
39,566
kWh
|
$1,208
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,310 | $450 | - | - |
$1,310
-
MMBtu
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,120 | $2,000 | - | - |
$1,120
-
MMBtu
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,057 | $4,527 |
$805
33,411
kWh
|
$1,252
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $38,165 | $11,480 |
$1,380
57,444
kWh
|
$1,860
-
kW-mo/yr
|
- | - | $(-75.0) | $35,000 | |
| TOTAL RECOMMENDED | $52,598 | $21,957 |
$3,075
130,421
kWh
|
$4,320
-
kW-mo/yr
|
$2,430
-
MMBtu
|
$7,848 | $(-75.0) | $35,000 | ||
| TOTAL IMPLEMENTED | $3,367 | $4,977 |
$805
33,411
kWh
|
$1,252
-
kW-mo/yr
|
$1,310
-
MMBtu
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs