Assessment Year | 1986 |
---|---|
Principal Product | PAINTS & PAINT RESINS |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 750
Tgal
|
Production Hrs. Annual | 2,990
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,639 | 686,987 |
kWh
|
$0.085 |
Natural Gas | $50,576 | 10,722 |
MMBtu
|
$4.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,385 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $841 | $500 |
$841
-
kWh
|
- | |
02 | 2.7261: Install timers and/or thermostats | $7,907 | $43 |
$85
879
kWh
|
$7,822
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,284 | $315 | - |
$1,284
-
MMBtu
|
|
04 | 2.7492: Use proper thickness of insulation on building envelope | $183 | $350 | - |
$183
-
MMBtu
|
|
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,210 | $300 | - |
$1,210
-
MMBtu
|
|
06 | 2.1222: Install turbulators | $674 | $400 | - |
$674
-
MMBtu
|
|
07 | 2.2437: Recover waste heat from equipment | $674 | $200 | - |
$674
-
MMBtu
|
|
08 | 2.4221: Install compressor air intakes in coolest locations | $478 | $50 |
$478
5,569
kWh
|
- | |
09 | 2.4312: Improve lubrication practices | $305 | - |
$305
3,517
kWh
|
- | |
10 | 2.7441: Replace broken windows and/or window sash | $4,405 | $1,500 | - |
$4,405
-
MMBtu
|
|
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,919 | $90 |
$1,919
22,567
kWh
|
- | |
TOTAL RECOMMENDED | $19,880 | $3,748 |
$3,628
32,532
kWh
|
$16,252
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,385 | $1,855 |
$3,543
31,653
kWh
|
$3,842
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs