| Assessment Year | 1986 |
|---|---|
| Principal Product | PLASTIC INJECTION-MOLD PARTS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 150,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $80,636 | 1,471,864 |
kWh
|
$0.055 |
| Natural Gas | $6,607 | 1,664 |
MMBtu
|
$3.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,434 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,958 | $500 |
$1,958
35,756
kWh
|
- | |
| 02 | 2.7229: Air condition only space necessary | $809 | $500 | - |
$809
-
MMBtu
|
|
| 03 | 2.7226: Use computer programs to optimize hvac performance | $2,508 | $177 |
$369
6,741
kWh
|
$2,139
-
MMBtu
|
|
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,552 | $190 | - |
$1,552
-
MMBtu
|
|
| 05 | 2.4312: Improve lubrication practices | $1,043 | - |
$1,043
19,050
kWh
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $578 | $200 |
$578
10,551
kWh
|
- | |
| 07 | 2.7492: Use proper thickness of insulation on building envelope | $189 | $280 | - |
$189
-
MMBtu
|
|
| 08 | 2.6218: Turn off equipment when not in use | $80 | $100 |
$80
1,465
kWh
|
- | |
| 09 | 2.7262: Separate controls of air handlers from ac/ heating systems | $305 | $400 |
$305
5,569
kWh
|
- | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,412 | $476 |
$1,412
25,791
kWh
|
- | |
| TOTAL RECOMMENDED | $10,434 | $2,823 |
$5,745
104,923
kWh
|
$4,689
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs