| Assessment Year | 2016 |
|---|---|
| Principal Product | Coring Bits and Reamers |
| NAICS | 333131: Mining Machinery and Equipment Manufacturing |
| SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 46 |
| Plant Area |
50,000
ft2
|
| Annual Production | 40,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $74,331 | 1,788,320 |
kWh
|
$0.042 |
| Electricity Demand | $128,564 | 6,988 |
kW-mo/yr
|
$18.40 |
| Electricity Fees | $1,185 | - |
|
- |
| Natural Gas | $21,103 | 3,177 |
MMBtu
|
$6.64 |
| TOTAL YEARLY COSTS | $225,183 | |||
| RECOMMENDED SAVINGS* | $23,984 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,358 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $14,626 | $14,109 | - | $14,626 | - | |
| 02 | 2.4224: Upgrade controls on compressors | $5,025 | $2,777 |
$5,025
120,900
kWh
|
- | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $1,367 | $1,665 |
$1,367
32,899
kWh
|
- | - | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $962 | $14 | - | - |
$962
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $737 | $871 |
$737
17,732
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $655 | $768 |
$655
15,753
kWh
|
- | - | |
| 07 | 2.6218: Turn off equipment when not in use | $612 | $440 |
$612
14,724
kWh
|
- | - | |
| TOTAL RECOMMENDED | $23,984 | $20,644 |
$8,396
202,008
kWh
|
$14,626 |
$962
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,358 | $6,535 |
$8,396
202,008
kWh
|
- |
$962
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs