ITAC Assessment: AT0122
ITAC logo
ITAC Assessment: AT0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product HOSIERY & SOCKS
NAICS
n/a
SIC 2252: Hosiery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area
n/a
Annual Production 120,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,553 3,475,381
kWh
Natural Gas $12,600 3,219
MMBtu
Fuel Oil #2 $41,553 11,875
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,114 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,480

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.6232: Install set-back timers $2,653 $2,068 $2,653
47,773
kWh
- - -
02 2.4312: Improve lubrication practices $3,019 - $3,019
54,220
kWh
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $821 - $821
14,654
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,359 $100 $1,359
24,326
kWh
- - -
05 2.4221: Install compressor air intakes in coolest locations $127 $300 $127
2,345
kWh
- - -
06 2.7261: Install timers and/or thermostats $605 $600 $605
10,844
kWh
- - -
07 2.2414: Use waste heat from hot flue gases to preheat $5,794 $10,000 - $1,345
-
MMBtu
$4,449
-
MMBtu
-
08 2.2135: Repair and eliminate steam leaks $5,036 $50 - $1,169
-
MMBtu
$3,867
-
MMBtu
-
09 2.1233: Analyze flue gas for proper air/fuel ratio $2,700 - - $673
-
MMBtu
$2,227
-
MMBtu
$(-200.0)
TOTAL RECOMMENDED $22,114 $13,118 $8,584
154,162
kWh
$3,187
-
MMBtu
$10,543
-
MMBtu
$(-200.0)
TOTAL IMPLEMENTED $12,480 $3,118 $4,744
85,288
kWh
$1,842
-
MMBtu
$6,094
-
MMBtu
$(-200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs