Assessment Year | 1989 |
---|---|
Principal Product | HOSIERY & SOCKS |
NAICS |
n/a
|
SIC | 2252: Hosiery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
n/a
|
Annual Production | 120,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,553 | 3,475,381 |
kWh
|
$0.056 |
Natural Gas | $12,600 | 3,219 |
MMBtu
|
$3.91 |
Fuel Oil #2 | $41,553 | 11,875 |
MMBtu
|
$3.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,114 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,480 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $2,653 | $2,068 |
$2,653
47,773
kWh
|
- | - | - | |
02 | 2.4312: Improve lubrication practices | $3,019 | - |
$3,019
54,220
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $821 | - |
$821
14,654
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,359 | $100 |
$1,359
24,326
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $127 | $300 |
$127
2,345
kWh
|
- | - | - | |
06 | 2.7261: Install timers and/or thermostats | $605 | $600 |
$605
10,844
kWh
|
- | - | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $5,794 | $10,000 | - |
$1,345
-
MMBtu
|
$4,449
-
MMBtu
|
- | |
08 | 2.2135: Repair and eliminate steam leaks | $5,036 | $50 | - |
$1,169
-
MMBtu
|
$3,867
-
MMBtu
|
- | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,700 | - | - |
$673
-
MMBtu
|
$2,227
-
MMBtu
|
$(-200.0) | |
TOTAL RECOMMENDED | $22,114 | $13,118 |
$8,584
154,162
kWh
|
$3,187
-
MMBtu
|
$10,543
-
MMBtu
|
$(-200.0) | ||
TOTAL IMPLEMENTED | $12,480 | $3,118 |
$4,744
85,288
kWh
|
$1,842
-
MMBtu
|
$6,094
-
MMBtu
|
$(-200.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs