Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

157

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Laboratory apparatus and furniture
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MI0423 #10 Y:2023 Analyze flue gas for proper air/fuel ratio $277 $1,360
MI0423 #09 Y:2023 Air condition only space necessary $1,771 $900
MI0423 #08 Y:2023 Install outside air damper / economizer on hvac unit $2,131 $1,500
MI0423 #07 Y:2023 Install occupancy sensors $4,508 $1,250
MI0423 #06 Y:2023 Install partitions to reduce size of conditioned space $6,580 $1,455
MI0423 #05 Y:2023 Modify refrigeration system to operate at a lower pressure $9,196 $27,500
MI0423 #04 Y:2023 Clean or color roof to reduce solar load $10,785 $37,678
MI0423 #03 Y:2023 Lower temperature during the winter season and vice-versa $22,808 $580
MI0423 #02 Y:2023 Utilize higher efficiency lamps and/or ballasts $26,513 $51,984
MI0423 #01 Y:2023 Turn off equipment when not in use $41,834 -
OR0650 #06 Y:2015 Use solar heat to make electricty $16,731 $135,510
OR0650 #05 Y:2015 Heat water during off-peak periods and store for later use $1,291 $4,404
OR0650 #04 Y:2015 Install occupancy sensors $1,001 $2,678
OR0650 #03 Y:2015 Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $719 $1,200
OR0650 #02 Y:2015 Improve combustion control capability $23,922 $24,660
OR0650 #01 Y:2015 Eliminate/reduce an operation $20,348 $2,295
SF0466 #06 Y:2015 Utilize higher efficiency lamps and/or ballasts $3,026 $4,733
SF0466 #05 Y:2015 Install occupancy sensors $5,556 $6,409
SF0466 #04 Y:2015 Use adjustable frequency drive or multiple speed motors on existing system $3,752 $2,224
SF0466 #03 Y:2015 Use adjustable frequency drive or multiple speed motors on existing system $10,885 $5,614