Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

146

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Ammunition, except for small arms
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OK0980 #06 Y:2017 Optimize plant power factor $13,258 $16,892
OK0980 #05 Y:2017 Use waste heat from hot flue gases to preheat $24,343 $31,350
OK0980 #04 Y:2017 Analyze flue gas for proper air/fuel ratio $23,198 $23,580
OK0980 #03 Y:2017 Utilize higher efficiency lamps and/or ballasts $1,611 $7,298
OK0980 #02 Y:2017 Use photocell controls $1,443 $4,790
OK0980 #01 Y:2017 Turn off equipment when not in use $12,254 $1,350
LE0439 #08 Y:2017 Utilize higher efficiency lamps and/or ballasts $31,023 $105,761
LE0439 #07 Y:2017 Utilize higher efficiency lamps and/or ballasts $6,903 $21,654
LE0439 #06 Y:2017 Eliminate leaks in inert gas and compressed air lines/ valves $2,992 $5,000
LE0439 #05 Y:2017 Utilize higher efficiency lamps and/or ballasts $3,559 $4,244
LE0439 #04 Y:2017 Treat and reuse rinse waters $35,049 $30,000
LE0439 #03 Y:2017 Use radiant heater for spot heating $17,188 $9,084
LE0439 #02 Y:2017 Install compressor air intakes in coolest locations $2,477 $600
LE0439 #01 Y:2017 Reduce the pressure of compressed air to the minimum required $4,940 $750
IA0510 #08 Y:2013 Install vinyl strip / high speed / air curtain doors $4,980 $1,290
IA0510 #07 Y:2013 Utilize higher efficiency lamps and/or ballasts $14,538 $30,502
IA0510 #06 Y:2013 Utilize higher efficiency lamps and/or ballasts $1,748 $7,018
IA0510 #05 Y:2013 Reduce the pressure of compressed air to the minimum required $4,723 $30
IA0510 #04 Y:2013 Eliminate leaks in inert gas and compressed air lines/ valves $12,760 $600
IA0510 #03 Y:2013 Utilize controls to operate equipment only when needed $13,742 $30,000