| Assessment Year | 2013 |
|---|---|
| Principal Product | Ammunition |
| NAICS | 332993: Ammunition (except Small Arms) Manufacturing |
| SIC | 3483: Ammunition, Except for Small Arms |
| Sales Range | less than $500 k |
| # of Employees | 900 |
| Plant Area |
1,001
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,625
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $745,379 | 22,766,533 |
kWh
|
$0.033 |
| Electricity Demand | $546,058 | 46,057 |
kW-mo/yr
|
$11.86 |
| Natural Gas | $829,694 | 188,457 |
MMBtu
|
$4.40 |
| Coal | $1,367,055 | 329,410 |
MMBtu
|
$4.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $118,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Coal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2113: Repair or replace steam traps | $58,322 | $6,395 | - | - |
$19,432
-
MMBtu
|
$38,890
-
MMBtu
|
|
| 02 | 2.2511: Insulate bare equipment | $7,547 | $2,769 | - | - |
$2,527
-
MMBtu
|
$5,020
-
MMBtu
|
|
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $13,742 | $30,000 |
$13,742
418,953
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,760 | $600 |
$8,539
260,350
kWh
|
$4,221
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,723 | $30 |
$3,161
96,360
kWh
|
$1,562
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,748 | $7,018 |
$657
20,157
kWh
|
$1,091
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,538 | $30,502 |
$5,489
167,342
kWh
|
$9,049
-
kW-mo/yr
|
- | - | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,980 | $1,290 |
$553
16,877
kWh
|
- |
$1,474
-
MMBtu
|
$2,953
-
MMBtu
|
|
| TOTAL RECOMMENDED | $118,360 | $78,604 |
$32,141
980,039
kWh
|
$15,923
-
kW-mo/yr
|
$23,433
-
MMBtu
|
$46,863
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Coal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs