Assessment Year | 2017 |
---|---|
Principal Product | Tank Ammunition and Milled Products |
NAICS | 332993: Ammunition (except Small Arms) Manufacturing |
SIC | 3483: Ammunition, Except for Small Arms |
Sales Range | $10 M to 50M |
# of Employees | 68 |
Plant Area |
283,349
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 7,140
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $506,779 | 9,515,855 |
kWh
|
$0.053 | |
Electricity Demand | $62,266 | 30,522 |
kW-mo/yr
|
$2.04 | |
Electricity Fees | $111,038 | - |
|
- | |
Natural Gas | $208,440 | 38,501 |
MMBtu
|
$5.41 | |
Waste Disposal Costs | |||||
Water Usage | $93,850 | 13,400 |
Tgal
|
$7.00 | |
TOTAL YEARLY COSTS | $982,373 | ||||
RECOMMENDED SAVINGS* | $104,131 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $12,372 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,940 | $750 |
$4,775
90,089
kWh
|
$165
-
kW-mo/yr
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,477 | $600 |
$2,367
44,665
kWh
|
$110
-
kW-mo/yr
|
- | - | |
03 | 2.7231: Use radiant heater for spot heating | $17,188 | $9,084 | - | - |
$17,188
-
MMBtu
|
- | |
04 | 3.4113: Treat and reuse rinse waters | $35,049 | $30,000 | - | - | - |
$35,049
-
Tgal
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,559 | $4,244 |
$3,218
60,715
kWh
|
$341
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,992 | $5,000 |
$2,878
54,309
kWh
|
$114
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,903 | $21,654 |
$6,036
113,891
kWh
|
$867
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $31,023 | $105,761 |
$29,138
549,780
kWh
|
$1,885
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $104,131 | $177,093 |
$48,412
913,449
kWh
|
$3,482
-
kW-mo/yr
|
$17,188
-
MMBtu
|
$35,049
-
Tgal
|
||
TOTAL IMPLEMENTED | $12,372 | $27,254 |
$11,281
212,865
kWh
|
$1,091
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs