380
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UU0294 #07 Y:2026 | 07 | 2026 | Reduce the pressure of compressed air to the minimum required | $1,090 | $230 |
n/a
|
| UU0294 #06 Y:2026 | 06 | 2026 | Turn off equipment when not in use | $3,000 | $550 |
n/a
|
| UU0294 #05 Y:2026 | 05 | 2026 | Install compressor air intakes in coolest locations | $1,180 | $3,030 |
n/a
|
| UU0294 #04 Y:2026 | 04 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,970 | $1,160 |
n/a
|
| UU0294 #03 Y:2026 | 03 | 2026 | Upgrade controls on compressors | $7,737 | $40,800 |
n/a
|
| UU0294 #02 Y:2026 | 02 | 2026 | Install adequate dryers on air lines to eliminate blowdown | $29,060 | $16,500 |
n/a
|
| UU0294 #01 Y:2026 | 01 | 2026 | Use optimum temperature | $4,230 | $4,540 |
n/a
|
| CM1035 #09 Y:2024 | 09 | 2024 | Utilize a central coolant system for cleaning and reuse of metal working fluid | $33,805 | $102,000 |
n/a
|
| CM1035 #08 Y:2024 | 08 | 2024 | Apply for tax-free status for energy purchases | $1,605 | - |
n/a
|
| CM1035 #07 Y:2024 | 07 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $61,867 | $29,430 |
n/a
|
| CM1035 #06 Y:2024 | 06 | 2024 | Insulate glazing, walls, ceilings, and roofs | $2,208 | $1,271 |
n/a
|
| CM1035 #05 Y:2024 | 05 | 2024 | Install occupancy sensors | $180 | $141 |
n/a
|
| CM1035 #04 Y:2024 | 04 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $526 | $124 |
n/a
|
| CM1035 #03 Y:2024 | 03 | 2024 | Use computer programs to optimize hvac performance | $324 | $330 |
n/a
|
| CM1035 #02 Y:2024 | 02 | 2024 | Adjust / maintain fork lift trucks for most efficient operation | $8,641 | $34,268 |
n/a
|
| CM1035 #01 Y:2024 | 01 | 2024 | Use solar heat to make electricty | $116,451 | $1,482,720 |
n/a
|
| CI0015 #08 Y:2023 | 08 | 2023 | Use most efficient type of electric motors | $1,262 | $1,310 | |
| CI0015 #07 Y:2023 | 07 | 2023 | Recover waste heat from equipment | $1,292 | $5,000 | |
| CI0015 #06 Y:2023 | 06 | 2023 | Utilize higher efficiency lamps and/or ballasts | $1,444 | $2,700 | |
| CI0015 #05 Y:2023 | 05 | 2023 | Replace fossil fuel equipment with electrical equipment | $1,958 | $3,500 |