ITAC Assessment: OK1063
ITAC logo
ITAC Assessment: OK1063
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Small arms components
NAICS 332994: Small Arms, Ordnance, and Ordnance Accessories Manufacturing
SIC 3484: Small Arms
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 25,000
ft2
Annual Production 250,000
units
Production Hrs. Annual 7,280
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,555 1,271,100
kWh
Electricity Demand $30,285 2,355
kW-mo/yr
Electricity Fees $2,674 -
Natural Gas $1,985 694
MMBtu
Waste Disposal Costs
Water Usage $1,552 252
Tgal
Water Disposal $903 252
Tgal
TOTAL YEARLY COSTS $100,954
RECOMMENDED SAVINGS* $6,369 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,892 $617 $1,892
37,844
kWh
-
02 2.4239: Eliminate or reduce compressed air usage $1,446 - $1,446
29,327
kWh
-
03 2.7232: Replace existing hvac unit with high efficiency model $1,123 $2,600 $236
4,723
kWh
$887
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,908 $6,335 $874
17,472
kWh
$1,034
-
kW-mo/yr
TOTAL RECOMMENDED $6,369 $9,552 $4,448
89,366
kWh
$1,921
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs