Assessment Year | 2024 |
---|---|
Principal Product | Small Arms and Ammunition |
NAICS | 332994: Small Arms, Ordnance, and Ordnance Accessories Manufacturing |
SIC | 3484: Small Arms |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
97,350
ft2
|
Annual Production | 90,000
units
|
Production Hrs. Annual | 6,032
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $155,245 | 3,596,115 |
kWh
|
$0.043 |
Electricity Demand | $189,254 | 9,869 |
kW-mo/yr
|
$19.18 |
Electricity Fees | $36,257 | - |
|
- |
Natural Gas | $34,882 | 5,298 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | $415,637 | |||
RECOMMENDED SAVINGS* | $225,607 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $116,451 | $1,482,720 |
$110,121
2,550,857
kWh
|
$6,330
-
kW-mo/yr
|
- | - | - | |
02 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $8,641 | $34,268 |
$321
7,428
kWh
|
- | - | $8,320 | - | |
03 | 2.7226: Use computer programs to optimize hvac performance | $324 | $330 |
$324
7,502
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $526 | $124 |
$279
6,462
kWh
|
$247
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $180 | $141 |
$56
1,294
kWh
|
$124
-
kW-mo/yr
|
- | - | - | |
06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,208 | $1,271 | - | - |
$2,208
-
MMBtu
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $61,867 | $29,430 | - |
$61,867
-
kW-mo/yr
|
- | - | - | |
08 | 2.8121: Apply for tax-free status for energy purchases | $1,605 | - | - | - | - | $1,605 | - | |
09 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $33,805 | $102,000 |
$(-844.6)
(-19,550)
kWh
|
- | - | - | $34,650 | |
TOTAL RECOMMENDED | $225,607 | $1,650,284 |
$110,256
2,553,993
kWh
|
$68,568
-
kW-mo/yr
|
$2,208
-
MMBtu
|
$9,925 | $34,650 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs