Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

382

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Screw machine products
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MU0054 #07 Y:2024 Install partitions to reduce size of conditioned space $349 -
MU0054 #06 Y:2024 Use proper thickness of insulation on building envelope $118 $272
MU0054 #05 Y:2024 Install occupancy sensors $1,296 -
MU0054 #04 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $1,876 $1,801
MU0054 #03 Y:2024 Reduce the pressure of compressed air to the minimum required $6,874 -
MU0054 #02 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $8,402 $28,100
MU0054 #01 Y:2024 Use optimum temperature $6,955 -
DL0235 #07 Y:2023 Adjust vents to minimize energy use $814 $1,500
DL0235 #06 Y:2023 Reduce ventilation air $1,085 -
DL0235 #05 Y:2023 Install vinyl strip / high speed / air curtain doors $646 $3,000
DL0235 #04 Y:2023 Utilize controls to operate equipment only when needed $24,674 $10,000
DL0235 #03 Y:2023 Utilize controls to operate equipment only when needed $2,885 $500
DL0235 #02 Y:2023 Install timers and/or thermostats $751 $800
DL0235 #01 Y:2023 Utilize controls to operate equipment only when needed $719 -
DL0222 #09 Y:2023 Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $1,888 $2,450
DL0222 #08 Y:2023 Utilize higher efficiency lamps and/or ballasts $6,152 $4,581
DL0222 #07 Y:2023 Use / purchase optimum sized compressor $4,366 $25,000
DL0222 #06 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $1,097 $3,000
DL0222 #05 Y:2023 Utilize higher efficiency lamps and/or ballasts $402 $871
DL0222 #04 Y:2023 Turn off equipment during breaks, reduce operating time $413 -