| Assessment Year | 2026 |
|---|---|
| Principal Product | Precision Machine Parts |
| NAICS | 332710: Machine Shops |
| SIC | 3451: Screw Machine Products |
| Sales Range | $1 M to 5M |
| # of Employees | 18 |
| Plant Area |
7,500
ft2
|
| Annual Production | 400,000
pieces
|
| Production Hrs. Annual | 3,900
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $42,925 | 361,178 |
kWh
|
$0.12 |
| Electricity Demand | $47,985 | 984 |
kW-mo/yr
|
$48.77 |
| Electricity Fees | $5,212 | - |
|
- |
| Natural Gas | $4,778 | 240 |
MMBtu
|
$19.91 |
| TOTAL YEARLY COSTS | $100,900 | |||
| RECOMMENDED SAVINGS* | $51,449 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,281 | - |
$2,110
17,734
kWh
|
$1,171
-
kW-mo/yr
|
|
| 02 | 2.7261: Install timers and/or thermostats | $603 | - |
$603
5,070
kWh
|
- | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,401 | $2,000 | - |
$2,401
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,850 | $4,000 |
$1,167
9,803
kWh
|
$683
-
kW-mo/yr
|
|
| 05 | 2.9112: Use solar heat to heat water | $42,290 | $125,212 |
$10,674
89,700
kWh
|
$31,616
-
kW-mo/yr
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,024 | $4,000 |
$674
5,212
kWh
|
$349
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $51,449 | $135,212 |
$15,228
127,519
kWh
|
$36,220
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs