ITAC Assessment: MU0082
ITAC logo
ITAC Assessment: MU0082
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Injection molds and rubber and plastic products
NAICS 332721: Precision Turned Product Manufacturing
SIC 3451: Screw Machine Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 85,000
ft2
Annual Production 200
units
Production Hrs. Annual 5,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $232,937 2,554,378
kWh
Electricity Demand $40,586 7,144
kW-mo/yr
Electricity Fees $31,194 -
Natural Gas $8,483 1,121
MMBtu
Other Energy $2,181 1
MMBtu
TOTAL YEARLY COSTS $315,381
RECOMMENDED SAVINGS* $29,091 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.2511: Insulate bare equipment $7,766 $11,356 $7,766
85,341
kWh
- - - -
02 2.3132: Recharge batteries on during off-peak demand periods $6,271 $1,380 - $5,367
-
kW-mo/yr
- - $905
03 2.3212: Optimize plant power factor $3,418 $40,181 - - $3,418 - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $5,902 - $5,844
64,220
kWh
$58
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $662 $380 $602
6,613
kWh
$60
-
kW-mo/yr
- - -
06 2.6218: Turn off equipment when not in use $556 $3,102 $556
6,109
kWh
- - - -
07 2.7135: Install occupancy sensors $331 $912 $264
2,902
kWh
$67
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $105 $363 $96
1,060
kWh
$8
-
kW-mo/yr
- - -
09 2.7231: Use radiant heater for spot heating $2,820 $5,865 - - - $2,820
-
MMBtu
-
10 2.7261: Install timers and/or thermostats $124 $240 - - - $124
-
MMBtu
-
11 2.7444: Close holes and openings in building such as broken windows $44 $71 - - - $44
-
MMBtu
-
12 4.821: Pay bills on time to avoid late fees $1,092 - - - - - $1,092
TOTAL RECOMMENDED $29,091 $63,850 $15,128
166,243
kWh
$5,560
-
kW-mo/yr
$3,418 $2,989
-
MMBtu
$1,996
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs