1,250
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Fabricated plate work (boiler shops) | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| LS2521 #07 Y:2025 | 07 | 2025 | Use solar heat to make electricty | $37,653 | $526,500 |
n/a
|
| LS2521 #06 Y:2025 | 06 | 2025 | Replace existing equipment with more suitable substitutes | $70,474 | $710,000 |
n/a
|
| LS2521 #05 Y:2025 | 05 | 2025 | Clean or color roof to reduce solar load | $3,125 | $12,153 |
n/a
|
| LS2521 #04 Y:2025 | 04 | 2025 | Utilize higher efficiency lamps and/or ballasts | $2,368 | $2,575 |
n/a
|
| LS2521 #03 Y:2025 | 03 | 2025 | Clean and maintain refrigerant condensers and towers | $746 | $392 |
n/a
|
| LS2521 #02 Y:2025 | 02 | 2025 | Utilize daylight whenever possible in lieu of artificial light | $796 | $300 |
n/a
|
| LS2521 #01 Y:2025 | 01 | 2025 | Install timers and/or thermostats | $1,212 | $25 |
n/a
|
| UL2511 #07 Y:2025 | 07 | 2025 | Use outside cold water source as a supply of cooling water | $65,206 | $43,234 |
n/a
|
| UL2511 #06 Y:2025 | 06 | 2025 | Use solar heat to make electricty | $33,929 | $245,037 |
n/a
|
| UL2511 #05 Y:2025 | 05 | 2025 | Install occupancy sensors | $3,468 | $1,480 |
n/a
|
| UL2511 #04 Y:2025 | 04 | 2025 | Utilize higher efficiency lamps and/or ballasts | $4,104 | $2,409 |
n/a
|
| UL2511 #03 Y:2025 | 03 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $7,714 | $9,750 |
n/a
|
| UL2511 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $4,222 | $720 |
n/a
|
| UL2511 #01 Y:2025 | 01 | 2025 | Reduce the pressure of compressed air to the minimum required | $4,525 | - |
n/a
|
| MU0077 #07 Y:2025 | 07 | 2025 | Install partitions to reduce size of conditioned space | $1,816 | $2,353 |
n/a
|
| MU0077 #06 Y:2025 | 06 | 2025 | Reduce space conditioning during non-working hours | $654 | - |
n/a
|
| MU0077 #05 Y:2025 | 05 | 2025 | Keep equipment clean | $1,593 | - |
n/a
|
| MU0077 #04 Y:2025 | 04 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $57 | $80 |
n/a
|
| MU0077 #03 Y:2025 | 03 | 2025 | Install vinyl strip / high speed / air curtain doors | $2,396 | $4,121 |
n/a
|
| MU0077 #02 Y:2025 | 02 | 2025 | Recover heat from exhausted steam, hot air or hot water | $8,641 | $62,943 |
n/a
|