1,094
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
MI0462 #05 Y:2025 | 05 | 2025 | Use solar heat to make electricty | $15,563 | $77,756 |
n/a
|
MI0462 #04 Y:2025 | 04 | 2025 | Clean or color roof to reduce solar load | $4,679 | $18,537 |
n/a
|
MI0462 #03 Y:2025 | 03 | 2025 | Install partitions to reduce size of conditioned space | $5,309 | $1,594 |
n/a
|
MI0462 #02 Y:2025 | 02 | 2025 | Lower temperature during the winter season and vice-versa | $4,582 | $1,260 |
n/a
|
MI0462 #01 Y:2025 | 01 | 2025 | Turn off equipment when not in use | $15,504 | $2,400 |
n/a
|
CI0049 #11 Y:2025 | 11 | 2025 | Use most efficient type of electric motors | $918 | $470 |
n/a
|
CI0049 #10 Y:2025 | 10 | 2025 | Use waste heat from hot flue gases to preheat | $5,572 | $11,000 |
n/a
|
CI0049 #09 Y:2025 | 09 | 2025 | Replace fossil fuel equipment with electrical equipment | $9,652 | $40,000 |
n/a
|
CI0049 #08 Y:2025 | 08 | 2025 | Use power during off-peak periods | $13,567 | $22,000 |
n/a
|
CI0049 #07 Y:2025 | 07 | 2025 | Adopt in-house material generation | $13,673 | $350,000 |
n/a
|
CI0049 #06 Y:2025 | 06 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $14,474 | $5,000 |
n/a
|
CI0049 #05 Y:2025 | 05 | 2025 | Adjust burners for efficient operation | $18,240 | $44,000 |
n/a
|
CI0049 #04 Y:2025 | 04 | 2025 | Use battery storage for demand control | $17,261 | $58,000 |
n/a
|
CI0049 #03 Y:2025 | 03 | 2025 | Adopt in-house material generation | $18,814 | $22,000 |
n/a
|
CI0049 #02 Y:2025 | 02 | 2025 | Replace fossil fuel equipment with electrical equipment | $28,480 | $125,000 |
n/a
|
CI0049 #01 Y:2025 | 01 | 2025 | Replace boiler | $31,771 | $18,000 |
n/a
|
SD0676 #11 Y:2025 | 11 | 2025 | Install common header on compressors | $2,478 | $2,050 |
n/a
|
SD0676 #10 Y:2025 | 10 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $9,179 | $8,868 |
n/a
|
SD0676 #09 Y:2025 | 09 | 2025 | Utilize a less expensive cooling method | $153,587 | $200,000 |
n/a
|
SD0676 #08 Y:2025 | 08 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $143,491 | - |
n/a
|