Assessment Year | 2025 |
---|---|
Principal Product | Heat Treating |
NAICS | 332811: Metal Heat Treating |
SIC | 3398: Metal Heat Treating |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
38,000
ft2
|
Annual Production | 6,800
units
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $136,838 | 989,195 |
kWh
|
$0.14 | |
Electricity Demand | $75,890 | 2,504 |
kW-mo/yr
|
$30.31 | |
Electricity Fees | $23,163 | - |
|
- | |
Natural Gas | $242,407 | 19,942 |
MMBtu
|
$12.16 | |
LPG | $15,360 | 5,833 |
MMBtu
|
$2.63 | |
Other Gas | $15,297 | 1 |
MMBtu
|
$15,297.00 | |
Other Energy | $40,814 | 53,128 |
MMBtu
|
$0.77 | |
Waste Disposal Costs | |||||
Water Usage | $2,740 | 474 |
Tgal
|
$5.78 | |
TOTAL YEARLY COSTS | $552,509 | ||||
RECOMMENDED SAVINGS* | $170,682 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Energy Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $31,771 | $18,000 |
$(-21,264.0)
(-153,754)
kWh
|
$(-10,184.0)
-
kW-mo/yr
|
$63,219
-
MMBtu
|
- | - | - | - | |
02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $28,480 | $125,000 | - | - |
$28,480
-
MMBtu
|
- | - | - | - | |
03 | 4.212: Adopt in-house material generation | $18,814 | $22,000 | - | - | - | - |
$40,814
-
MMBtu
|
- | $(-22,000.0) | |
04 | 2.3141: Use battery storage for demand control | $17,261 | $58,000 |
$2,082
15,056
kWh
|
$15,179
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.1133: Adjust burners for efficient operation | $16,500 | $44,000 | - | - |
$16,500
-
MMBtu
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,474 | $5,000 |
$10,828
78,294
kWh
|
$3,646
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 4.212: Adopt in-house material generation | $13,673 | $175,000 | - | - | - | - | - | $13,673 | - | |
08 | 2.3137: Use power during off-peak periods | $13,567 | $22,000 | - |
$13,567
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.1321: Replace fossil fuel equipment with electrical equipment | $9,652 | $40,000 |
$(-4,810.0)
(-34,778)
kWh
|
$(-898.0)
-
kW-mo/yr
|
- |
$15,360
-
MMBtu
|
- | - | - | |
10 | 2.2442: Preheat combustion air with waste heat | $5,572 | $11,000 | - | - |
$5,572
-
MMBtu
|
- | - | - | - | |
11 | 2.4133: Use most efficient type of electric motors | $918 | $470 |
$713
5,158
kWh
|
$205
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $170,682 | $520,470 |
$(-12,451.0)
(-90,024)
kWh
|
$21,515
-
kW-mo/yr
|
$113,771
-
MMBtu
|
$15,360
-
MMBtu
|
$40,814
-
MMBtu
|
$13,673 | $(-22,000.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Energy Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs