Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

500

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Asphalt felts and coatings
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
AM0871 #10 Y:2022 Make a practice of turning off lights when not needed $525 -
AM0871 #09 Y:2022 Utilize higher efficiency lamps and/or ballasts $694 $588
AM0871 #08 Y:2022 Apply for tax-free status for energy purchases $3,600 $2,000
AM0871 #07 Y:2022 Use adjustable frequency drive or multiple speed motors on existing system $1,880 $2,700
AM0871 #06 Y:2022 Install occupancy sensors $1,890 $3,600
AM0871 #05 Y:2022 Utilize energy-efficient belts and other improved mechanisms $2,678 $1,280
AM0871 #04 Y:2022 Use synthetic lubricant $3,265 $500
AM0871 #03 Y:2022 Optimize plant power factor $6,228 $23,380
AM0871 #02 Y:2022 Reduce the pressure of compressed air to the minimum required $6,840 $30
AM0871 #01 Y:2022 Insulate bare equipment $7,430 $10,320
MA0846 #06 Y:2022 Turn off equipment during breaks, reduce operating time $674 $3,293
MA0846 #05 Y:2022 Install occupancy sensors $1,483 $4,908
MA0846 #04 Y:2022 Reduce the pressure of compressed air to the minimum required $6,290 $625
MA0846 #03 Y:2022 Use adjustable frequency drive or multiple speed motors on existing system $33,534 $15,450
MA0846 #02 Y:2022 Insulate bare equipment $10,916 $5,542
MA0846 #01 Y:2022 Use solar heat to make electricty $128,459 $1,302,718
MA0830 #06 Y:2021 Reduce temperature of process equipment when on standby $4,017 $2,500
MA0830 #05 Y:2021 Use adjustable frequency drive or multiple speed motors on existing system $35,055 $20,800
MA0830 #04 Y:2021 Moderate cooling tower outlet temperature $9,470 $2,500
MA0830 #03 Y:2021 Recover waste heat from equipment $15,862 $65,410