ITAC Assessment: MA0830
ITAC logo
ITAC Assessment: MA0830
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Roofing shingles
NAICS 324122: Asphalt Shingle and Coating Materials Manufacturing
SIC 2952: Asphalt Felts and Coatings
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 152,000
ft2
Annual Production 313,583
ton
Production Hrs. Annual 4,900
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $901,435 8,445,150
kWh
Electricity Demand $454,837 21,057
kW-mo/yr
Electricity Fees $1,080 -
Natural Gas $1,031,865 127,679
MMBtu
Waste Disposal Costs
Water Usage $154,349 16,159
Tgal
Water Disposal $15,538 629
Tgal
TOTAL YEARLY COSTS $2,559,104
RECOMMENDED SAVINGS* $223,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2449: Recover heat from exhausted steam, hot air or hot water $118,337 $192,000 - $118,337
-
MMBtu
02 2.1113: Reduce combustion air flow to optimum $40,790 $80,000 - $40,790
-
MMBtu
03 2.2437: Recover waste heat from equipment $15,862 $65,410 - $15,862
-
MMBtu
04 2.2611: Moderate cooling tower outlet temperature $9,470 $2,500 $9,470
88,723
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,055 $20,800 $35,055
328,417
kWh
-
06 2.6241: Reduce temperature of process equipment when on standby $4,017 $2,500 - $4,017
-
MMBtu
TOTAL RECOMMENDED $223,531 $363,210 $44,525
417,140
kWh
$179,006
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs