| Assessment Year | 2023 |
|---|---|
| Principal Product | Cookies |
| NAICS | 311821: Cookie and Cracker Manufacturing |
| SIC | 2052: Cookies and Crackers |
| Sales Range | $1 M to 5M |
| # of Employees | 24 |
| Plant Area |
42,000
ft2
|
| Annual Production | 120,000
units
|
| Production Hrs. Annual | 6,672
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,810 | 261,019 |
kWh
|
$0.14 |
| Electricity Demand | $26,123 | 671 |
kW-mo/yr
|
$38.93 |
| Natural Gas | $40,550 | 2,126 |
MMBtu
|
$19.08 |
| TOTAL YEARLY COSTS | $103,483 | |||
| RECOMMENDED SAVINGS* | $101,730 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $51,577 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $18,276 | - | - | - | $18,276 | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $738 | $50 |
$535
3,800
kWh
|
$203
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,662 | $6,270 |
$8,082
57,362
kWh
|
$4,425
-
kW-mo/yr
|
- | - | $1,155 | |
| 04 | 2.2425: Use flue gases to heat process or service water | $17,278 | $24,708 | - | - | - |
$17,278
-
MMBtu
|
- | |
| 05 | 2.2511: Insulate bare equipment | $937 | $3,563 | - | - | - |
$937
-
MMBtu
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $50,839 | $316,988 |
$50,839
272,744
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $101,730 | $351,579 |
$59,456
333,906
kWh
|
$4,628
-
kW-mo/yr
|
$18,276 |
$18,215
-
MMBtu
|
$1,155 | ||
| TOTAL IMPLEMENTED | $51,577 | $317,038 |
$51,374
276,544
kWh
|
$203
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs