Assessment Year | 2005 |
---|---|
Principal Product | Traffic paint |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $5 M to 10M |
# of Employees | 22 |
Plant Area |
60,000
ft2
|
Annual Production | 9,000
Tgal
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,832 | 457,200 |
kWh
|
$0.13 |
Electricity Demand | $23,605 | 3,882 |
kW-mo/yr
|
$6.08 |
Electricity Fees | $190 | - |
|
- |
Natural Gas | $37,820 | 3,341 |
MMBtu
|
$11.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,145 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,375 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $15,507 | $6,435 | - | - |
$15,507
-
MMBtu
|
|
02 | 2.1224: Replace boiler | $5,500 | $15,900 | - | - |
$5,500
-
MMBtu
|
|
03 | 2.3212: Optimize plant power factor | $5,270 | $5,200 | - |
$5,270
-
kW-mo/yr
|
- | |
04 | 2.2511: Insulate bare equipment | $2,868 | $3,920 |
$2,544
34,100
kWh
|
$324
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $29,145 | $31,455 |
$2,544
34,100
kWh
|
$5,594
-
kW-mo/yr
|
$21,007
-
MMBtu
|
||
TOTAL IMPLEMENTED | $18,375 | $10,355 |
$2,544
34,100
kWh
|
$324
-
kW-mo/yr
|
$15,507
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs