165
matching recommendations
$
$
ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | Wood pallets and skids | |
3+ Characters Required for Products |
ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
AS0525 #08 Y:2022 | 08 | 2022 | Maintain machines to reduce leaks | $705 | $1,992 | |
AS0525 #07 Y:2022 | 07 | 2022 | Use photocell controls | $894 | $144 | |
AS0525 #06 Y:2022 | 06 | 2022 | Utilize higher efficiency lamps and/or ballasts | $6,862 | $6,763 | |
AS0525 #05 Y:2022 | 05 | 2022 | Apply for investment incentives | $17,475 | $500 | |
AS0525 #04 Y:2022 | 04 | 2022 | Use adjustable frequency drive or multiple speed motors on existing system | $17,910 | $12,950 | |
AS0525 #03 Y:2022 | 03 | 2022 | Begin a practice of predictive / preventative maintenance | $22,011 | $1,900 | |
AS0525 #02 Y:2022 | 02 | 2022 | Add air shields to trucks to increase fuel mileage | $32,935 | $15,560 | |
AS0525 #01 Y:2022 | 01 | 2022 | Replace fossil fuel equipment with electrical equipment | $66,619 | $458,235 | |
LE0525 #06 Y:2022 | 06 | 2022 | Use adjustable frequency drive or multiple speed motors on existing system | $4,480 | $20,000 | |
LE0525 #05 Y:2022 | 05 | 2022 | Burn wood by-products for heat | $41,476 | $130,000 | |
LE0525 #04 Y:2022 | 04 | 2022 | Utilize higher efficiency lamps and/or ballasts | $763 | $2,001 | |
LE0525 #03 Y:2022 | 03 | 2022 | Use adjustable frequency drive or multiple speed motors on existing system | $108,808 | $250,000 | |
LE0525 #02 Y:2022 | 02 | 2022 | Eliminate or reduce compressed air usage | $6,698 | $5,000 | |
LE0525 #01 Y:2022 | 01 | 2022 | Reduce the pressure of compressed air to the minimum required | $993 | $150 | |
UA3029 #06 Y:2013 | 06 | 2013 | Install timers and/or thermostats | $1,023 | $330 | |
UA3029 #05 Y:2013 | 05 | 2013 | Utilize higher efficiency lamps and/or ballasts | $1,101 | $907 | |
UA3029 #04 Y:2013 | 04 | 2013 | Reduce the pressure of compressed air to the minimum required | $858 | $1,060 | |
UA3029 #03 Y:2013 | 03 | 2013 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,059 | $800 | |
UA3029 #02 Y:2013 | 02 | 2013 | Size electric motors for peak operating efficiency | $8,202 | $7,598 | |
UA3029 #01 Y:2013 | 01 | 2013 | Optimize plant power factor | $24,921 | $9,630 |