Assessment Year | 2022 |
---|---|
Principal Product | Wood Pallets |
NAICS | 321920: Wood Container and Pallet Manufacturing |
SIC | 2448: Wood Pallets and Skids |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
871,200
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 4,652
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $164,873 | 1,742,760 |
kWh
|
$0.095 | |
Electricity Demand | $33,059 | 5,540 |
kW-mo/yr
|
$5.97 | |
Electricity Fees | $14,207 | - |
|
- | |
LPG | $112,650 | 4,834 |
MMBtu
|
$23.30 | |
Fuel Oil #1 | $222,480 | 5,696 |
MMBtu
|
$39.06 | |
Waste Disposal Costs | |||||
Water Usage | $4,457 | 488 |
Tgal
|
$9.12 | |
TOTAL YEARLY COSTS | $551,726 | ||||
RECOMMENDED SAVINGS* | $165,411 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $97,898 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Fuel Oil #1 Savings | Water Usage Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $66,619 | $458,235 |
$(-45,139.0)
(-477,157)
kWh
|
- | - |
$104,258
-
MMBtu
|
- | - | - | $7,500 | |
02 | 2.8223: Add air shields to trucks to increase fuel mileage | $32,935 | $15,560 | - | - | - | - |
$32,935
-
MMBtu
|
- | - | - | |
03 | 4.611: Begin a practice of predictive / preventative maintenance | $22,011 | $1,900 |
$18,978
200,698
kWh
|
$3,033
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,910 | $12,950 |
$16,648
175,978
kWh
|
$1,262
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 4.812: Apply for investment incentives | $17,475 | $500 | - | - | $3,495 | - | - | - | - | $13,980 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,862 | $6,763 |
$5,684
60,081
kWh
|
$468
-
kW-mo/yr
|
- | - | - | - | $710 | - | |
07 | 2.7134: Use photocell controls | $894 | $144 |
$751
7,934
kWh
|
$143
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 3.7311: Maintain machines to reduce leaks | $705 | $1,992 | - | - | - | - | - |
$705
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $165,411 | $498,044 |
$(-3,078.0)
(-32,466)
kWh
|
$4,906
-
kW-mo/yr
|
$3,495 |
$104,258
-
MMBtu
|
$32,935
-
MMBtu
|
$705
-
Tgal
|
$710 | $21,480 | ||
TOTAL IMPLEMENTED | $97,898 | $39,665 |
$41,310
436,757
kWh
|
$4,763
-
kW-mo/yr
|
$3,495 | - |
$32,935
-
MMBtu
|
$705
-
Tgal
|
$710 | $13,980 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Fuel Oil #1 Savings | Water Usage Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs