25
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Potato chips, corn chips, and similar snacks | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| MZ0351 #08 Y:2023 | 08 | 2023 | Change product design to reduce energy requirements | $42,244 | $83,200 | |
| MZ0351 #07 Y:2023 | 07 | 2023 | Insulate bare equipment | $1,019 | $814 | |
| MZ0351 #06 Y:2023 | 06 | 2023 | Lower temperature during the winter season and vice-versa | $1,304 | - | |
| MZ0351 #05 Y:2023 | 05 | 2023 | Recover waste heat from equipment | $72,794 | $24,018 | |
| MZ0351 #04 Y:2023 | 04 | 2023 | Use adjustable frequency drive or multiple speed motors on existing system | $49,137 | $23,955 | |
| MZ0351 #03 Y:2023 | 03 | 2023 | Eliminate or reduce compressed air usage | $9,603 | $3,000 | |
| MZ0351 #02 Y:2023 | 02 | 2023 | Reduce the pressure of compressed air to the minimum required | $9,533 | $640 | |
| MZ0351 #01 Y:2023 | 01 | 2023 | Install compressor air intakes in coolest locations | $14,579 | $16,300 | |
| MZ0226 #06 Y:2017 | 06 | 2017 | Repair furnaces and oven doors so that they seal efficiently | $414 | $220 | |
| MZ0226 #05 Y:2017 | 05 | 2017 | Install compressor air intakes in coolest locations | $8,703 | $1,760 | |
| MZ0226 #04 Y:2017 | 04 | 2017 | Use waste heat from hot flue gases to preheat | $11,081 | $4,960 | |
| MZ0226 #03 Y:2017 | 03 | 2017 | Install / repair insulation on steam lines | $2,988 | $1,115 | |
| MZ0226 #02 Y:2017 | 02 | 2017 | Utilize energy-efficient belts and other improved mechanisms | $4,166 | - | |
| MZ0226 #01 Y:2017 | 01 | 2017 | Utilize higher efficiency lamps and/or ballasts | $2,015 | $5,450 | |
| MZ0061 #11 Y:2010 | 11 | 2010 | Reduce space conditioning during non-working hours | $4,994 | $5,000 | |
| MZ0061 #10 Y:2010 | 10 | 2010 | Use or replace with energy efficient substitutes | $250,000 | $1,500,000 | |
| MZ0061 #09 Y:2010 | 09 | 2010 | Reduce illumination to minimum necessary levels | $2,880 | - | |
| MZ0061 #08 Y:2010 | 08 | 2010 | Reduce scrap production | $92,766 | $100,000 | |
| MZ0061 #07 Y:2010 | 07 | 2010 | Eliminate leaks in inert gas and compressed air lines/ valves | $62,160 | $3,680 | |
| MZ0061 #06 Y:2010 | 06 | 2010 | Reduce the pressure of compressed air to the minimum required | $20,184 | - |