Assessment Year | 2010 |
---|---|
Principal Product | large and mini rice cakes |
NAICS | 311919: Other Snack Food Manufacturing |
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
80,000
ft2
|
Annual Production | 500
ton
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $819,037 | 16,101,552 |
kWh
|
$0.051 |
Electricity Demand | $621,509 | 34,528 |
kW-mo/yr
|
$18.00 |
Natural Gas | $77,667 | 39,269 |
MMBtu
|
$1.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $476,781 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $223,294 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $145 | $300 | - | - |
$145
-
MMBtu
|
|
02 | 2.2515: Use optimum thickness insulation | $79 | $1,200 | - | - |
$79
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $36,947 | $2,160 |
$28,347
318,507
kWh
|
$8,600
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $607 | $150 |
$460
5,440
kWh
|
$147
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,019 | - |
$6,019
67,637
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $20,184 | - |
$20,184
226,784
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $62,160 | $3,680 |
$62,160
94,720
kWh
|
- | - | |
08 | 3.1192: Reduce scrap production | $92,766 | $100,000 |
$92,766
1,036,882
kWh
|
- | - | |
09 | 2.7111: Reduce illumination to minimum necessary levels | $2,880 | - |
$2,210
24,832
kWh
|
$670
-
kW-mo/yr
|
- | |
10 | 2.4322: Use or replace with energy efficient substitutes | $250,000 | $1,500,000 |
$250,000
2,808,988
kWh
|
- | - | |
11 | 2.7224: Reduce space conditioning during non-working hours | $4,994 | $5,000 |
$4,994
56,110
kWh
|
- | - | |
TOTAL RECOMMENDED | $476,781 | $1,612,490 |
$467,140
4,639,900
kWh
|
$9,417
-
kW-mo/yr
|
$224
-
MMBtu
|
||
TOTAL IMPLEMENTED | $223,294 | $112,340 |
$214,470
1,800,640
kWh
|
$8,600
-
kW-mo/yr
|
$224
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs