Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

96

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Dairy products
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MZ0257 #12 Y:2018 Minimize water usage $37,478 -
MZ0257 #11 Y:2018 Utilize energy-efficient belts and other improved mechanisms $1,204 -
MZ0257 #10 Y:2018 Use compressor air filters $222 $200
MZ0257 #09 Y:2018 Repair faulty insulation in furnaces, boilers, etc $1,294 $5,330
MZ0257 #08 Y:2018 Repair furnaces and oven doors so that they seal efficiently $839 $1,900
MZ0257 #07 Y:2018 Use optimum thickness insulation $7,678 $7,480
MZ0257 #06 Y:2018 Insulate bare equipment $600 $752
MZ0257 #05 Y:2018 Reduce the pressure of compressed air to the minimum required $1,826 -
MZ0257 #04 Y:2018 Install compressor air intakes in coolest locations $1,225 $1,800
MZ0257 #03 Y:2018 Install occupancy sensors $1,472 $3,025
MZ0257 #02 Y:2018 Utilize higher efficiency lamps and/or ballasts $869 $5,414
MZ0257 #01 Y:2018 Utilize higher efficiency lamps and/or ballasts $490 $2,925
BD0393 #07 Y:2011 Install occupancy sensors $155 $300
BD0393 #06 Y:2011 Reduce the pressure of compressed air to the minimum required $201 $10
BD0393 #05 Y:2011 Install compressor air intakes in coolest locations $2,084 $1,500
BD0393 #04 Y:2011 Use most efficient type of electric motors $7,570 $9,600
BD0393 #03 Y:2011 Utilize higher efficiency lamps and/or ballasts $14,288 $107,000
BD0393 #02 Y:2011 Direct warmest air to combustion intake $8,510 $10,000
BD0393 #01 Y:2011 Replace obsolete burners with more efficient ones $54,406 $4,000
BD0289 #11 Y:2005 Install automatic packing equipment $57,600 $105,000