| Assessment Year | 2005 |
|---|---|
| Principal Product | Natural Dairy Products |
| NAICS | 311513: Cheese Manufacturing |
| SIC | 2021: Creamery Butter |
| Sales Range | $1 M to 5M |
| # of Employees | 20 |
| Plant Area |
50,000
ft2
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 5,304
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,650 | 608,161 |
kWh
|
$0.039 |
| Electricity Demand | $29,921 | 2,445 |
kW-mo/yr
|
$12.24 |
| Electricity Fees | $1,621 | - |
|
- |
| Natural Gas | $127,699 | 17,744 |
MMBtu
|
$7.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $76,471 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $73,500 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $6,189 | $3,500 |
$902
23,202
kWh
|
$5,287
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $4,957 | - | - |
$4,957
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $2,275 | $6,900 |
$2,528
58,397
kWh
|
$1,270
-
kW-mo/yr
|
$(-1,523.0)
-
MMBtu
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,225 | $1,500 |
$603
15,494
kWh
|
$622
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7135: Install occupancy sensors | $910 | $1,050 |
$455
11,696
kWh
|
$455
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $694 | $900 |
$131
3,355
kWh
|
$563
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.2531: Re-size charging openings or add movable cover or door | $770 | $1,780 | - | - |
$770
-
MMBtu
|
- | - | |
| 08 | 2.3137: Use power during off-peak periods | $484 | - | - |
$484
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.2136: Install / repair insulation on steam lines | $315 | $576 | - | - |
$315
-
MMBtu
|
- | - | |
| 10 | 4.821: Pay bills on time to avoid late fees | $1,052 | - | - | - | - | - | $1,052 | |
| 11 | 4.441: Install automatic packing equipment | $57,600 | $105,000 | - | - | - | $57,600 | - | |
| TOTAL RECOMMENDED | $76,471 | $121,206 |
$4,619
112,144
kWh
|
$13,638
-
kW-mo/yr
|
$(-438.0)
-
MMBtu
|
$57,600 | $1,052 | ||
| TOTAL IMPLEMENTED | $73,500 | $118,806 |
$3,885
93,295
kWh
|
$12,453
-
kW-mo/yr
|
$(-438.0)
-
MMBtu
|
$57,600 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs