Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

104

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Waste management and remediation services
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MUCM41 #07 Y:2026 Maintain machines to reduce leaks $572 $19
MUCM41 #06 Y:2026 Utilize sensors controlling roof and wall openings $4,966 $1,875
MUCM41 #05 Y:2026 Reduce ventilation air $585 -
MUCM41 #04 Y:2026 Reduce illumination to minimum necessary levels $50 -
MUCM41 #03 Y:2026 Utilize controls to operate equipment only when needed $64 -
MUCM41 #02 Y:2026 Install vinyl strip / high speed / air curtain doors $7,806 $19,925
MUCM41 #01 Y:2026 Install timers and/or thermostats $9,797 $969
UU0250 #06 Y:2024 Turn off equipment during breaks, reduce operating time $6,753 $5,720
UU0250 #05 Y:2024 Utilize higher efficiency lamps and/or ballasts $6,806 $13,208
UU0250 #04 Y:2024 Eliminate or reduce compressed air usage $8,795 $5,760
UU0250 #03 Y:2024 Burn a less expensive grade of fuel $11,024 $16,000
UU0250 #02 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $18,742 $49,723
UU0250 #01 Y:2024 Optimize plant power factor $42,332 $60,420
IP0183 #04 Y:2023 Optimize plant power factor $71,584 $212,913
IP0183 #03 Y:2023 Use radiant heater for spot heating $8,695 $19,367
IP0183 #02 Y:2023 Increase amount of condensate returned $48,374 $55,000
IP0183 #01 Y:2023 Utilize higher efficiency lamps and/or ballasts $43,443 $37,653
MU0017 #05 Y:2022 Close holes and openings in building such as broken windows $719 $75
MU0017 #04 Y:2022 Utilize higher efficiency lamps and/or ballasts $364 $555
MU0017 #03 Y:2022 Reduce illumination to minimum necessary levels $31 -