ITAC Assessment: UU0250
ITAC logo
ITAC Assessment: UU0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Recycled Tires
NAICS 562920: Materials Recovery Facilities
SIC 4953: Refuse Systems
Sales Range less than $500
k
# of Employees 50
Plant Area 38,000
ft2
Annual Production 1
units
Production Hrs. Annual 6,240
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $275,542 7,642,942
kWh
Electricity Demand $410,411 29,793
kW-mo/yr
Electricity Fees $276,110 -
Natural Gas $26,723 2,220
MMBtu
Waste Disposal Costs
Water Usage $13,451 1,370
Tgal
TOTAL YEARLY COSTS $1,002,237
RECOMMENDED SAVINGS* $94,452 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $75,710

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $42,332 $60,420 - - $42,332
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,742 $49,723 $18,742
520,614
kWh
- -
03 2.1331: Burn a less expensive grade of fuel $11,024 $16,000 - - $11,024
04 2.4239: Eliminate or reduce compressed air usage $8,795 $5,760 $8,795
244,304
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $6,806 $13,208 $3,142
87,279
kWh
$3,239
-
kW-mo/yr
$425
06 2.6212: Turn off equipment during breaks, reduce operating time $6,753 $5,720 $6,753
187,611
kWh
- -
TOTAL RECOMMENDED $94,452 $150,831 $37,432
1,039,808
kWh
$3,239
-
kW-mo/yr
$53,781
TOTAL IMPLEMENTED $75,710 $101,108 $18,690
519,194
kWh
$3,239
-
kW-mo/yr
$53,781
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs