Assessment Year | 2002 |
---|---|
Principal Product | Wellhead equipment |
NAICS |
n/a
|
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 46 |
Plant Area |
30,000
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 3,744
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,556 | 554,960 |
kWh
|
$0.064 |
Electricity Fees | $1,252 | - |
|
- |
Natural Gas | $7,953 | 869 |
MMBtu
|
$9.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,471 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,643 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $1,932 | $1,499 | - | - |
$1,932
-
MMBtu
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,591 | $210 |
$1,530
23,799
kWh
|
$61 | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $1,237 | - |
$1,189
18,495
kWh
|
$48 | - | - | |
04 | 2.7145: Install skylights | $1,206 | $1,660 |
$1,160
18,042
kWh
|
$46 | - | - | |
05 | 4.611: Begin a practice of predictive / preventative maintenance | $1,505 | $2,255 | - | - | - | $1,505 | |
TOTAL RECOMMENDED | $7,471 | $5,624 |
$3,879
60,336
kWh
|
$155 |
$1,932
-
MMBtu
|
$1,505 | ||
TOTAL IMPLEMENTED | $4,643 | $5,414 |
$1,160
18,042
kWh
|
$46 |
$1,932
-
MMBtu
|
$1,505 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs