ITAC Assessment: WV0277
ITAC logo
ITAC Assessment: WV0277
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Poultry fat and feather mill
NAICS 311613: Rendering and Meat Byproduct Processing
SIC 2077: Animal and Marine Fats and Oils
Sales Range $5
M
to 10
M
# of Employees 28
Plant Area 80,000
ft2
Annual Production 72,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,846 9,690,000
kWh
Electricity Demand $212,899 52,153
kW-mo/yr
Electricity Fees $83,524 -
Natural Gas $1,244,038 236,440
MMBtu
Fuel Oil #2 $1,953,673 251,242
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $405,157 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $171,582

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.2414: Use waste heat from hot flue gases to preheat $110,201 $2,195 - - - $22,040
-
MMBtu
$88,161
-
MMBtu
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $10,711 $1,000 - - - $2,142
-
MMBtu
$8,569
-
MMBtu
- -
03 3.4151: Minimize water usage $56,297 $17,800 - - - $9,364
-
MMBtu
$37,456
-
MMBtu
$9,477
-
Tgal
-
04 3.5311: Recover and reuse waste material $65,102 $250,000 - - - $230
-
MMBtu
$1,172
-
MMBtu
- $63,700
-
lb
05 2.2511: Insulate bare equipment $61,699 $29,824 - - - $12,340
-
MMBtu
$49,359
-
MMBtu
- -
06 2.2135: Repair and eliminate steam leaks $40,926 $450 - - - $8,185
-
MMBtu
$32,741
-
MMBtu
- -
07 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $40,046 $1,050 $34,219
849,700
kWh
$6,667
-
kW-mo/yr
$(-840.0) - - - -
08 2.3212: Optimize plant power factor $10,739 $62,060 - - $10,739 - - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,204 $5,175 $5,192
128,920
kWh
$1,012
-
kW-mo/yr
- - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,044 - $874
21,690
kWh
$170
-
kW-mo/yr
- - - - -
11 2.4231: Reduce the pressure of compressed air to the minimum required $1,257 $70 $1,057
26,263
kWh
$200
-
kW-mo/yr
- - - - -
12 2.4221: Install compressor air intakes in coolest locations $931 $470 $779
19,379
kWh
$152
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $405,157 $370,094 $42,121
1,045,952
kWh
$8,201
-
kW-mo/yr
$9,899 $54,301
-
MMBtu
$217,458
-
MMBtu
$9,477
-
Tgal
$63,700
-
lb
TOTAL IMPLEMENTED $171,582 $99,629 $40,468
1,004,883
kWh
$7,879
-
kW-mo/yr
$9,899 $22,667
-
MMBtu
$90,669
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs