Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Aircraft manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UU0299 #07 Y:2026 Use adjustable frequency drive or multiple speed motors on existing system $2,000 $15,100
UU0299 #06 Y:2026 Install occupancy sensors $15,973 $56,500
UU0299 #05 Y:2026 Eliminate or reduce compressed air usage $2,526 $21,800
UU0299 #04 Y:2026 Minimize use of outside make-up air for ventilation except when used for economizer cycle $761 $220
UU0299 #03 Y:2026 Install vinyl strip / high speed / air curtain doors $6,775 $20,100
UU0299 #02 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $6,120 $2,840
UU0299 #01 Y:2026 Use battery storage for demand control $36,773 $132,000
UU0261 #06 Y:2024 Use or replace with energy efficient substitutes $400 $5,940
UU0261 #05 Y:2024 Eliminate or reduce compressed air usage $1,386 $8,280
UU0261 #04 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $2,063 $9,140
UU0261 #03 Y:2024 Consider use / purchase of bulk materials where possible $12,100 $21,600
UU0261 #02 Y:2024 Replace existing hvac unit with high efficiency model $2,592 $37,200
UU0261 #01 Y:2024 Use solar heat to make electricty $22,296 $572,100
UU0060 #07 Y:2004 Change rate schedules or other changes in utility service $4,897 $200
UU0060 #06 Y:2004 Reschedule plant operations or reduce load to avoid peaks $2,853 -
UU0060 #05 Y:2004 Insulate bare equipment $309 $723
UU0060 #04 Y:2004 Minimize operation of equipment maintained in standby condition $3,047 $2,600
UU0060 #03 Y:2004 Install soft-start to eliminate nuisance trips $5,059 $4,000
UU0060 #02 Y:2004 Eliminate or reduce compressed air usage $5,695 $4,800
UU0060 #01 Y:2004 Use / purchase optimum sized compressor $3,202 $13,200