ITAC Assessment: UU0060
ITAC logo
ITAC Assessment: UU0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product aircraft parts
NAICS 336411: Aircraft Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 276
Plant Area 232,000
ft2
Annual Production 291,500
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,423 5,737,240
kWh
Electricity Demand $77,879 12,584
kW-mo/yr
Electricity Fees $28,560 -
Natural Gas $59,383 11,754
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,158

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.4226: Use / purchase optimum sized compressor $3,202 $13,200 $(-642.0)
(-27,502)
kWh
$3,844
-
kW-mo/yr
-
02 2.4239: Eliminate or reduce compressed air usage $5,695 $4,800 $87
3,741
kWh
$5,608
-
kW-mo/yr
-
03 2.4112: Install soft-start to eliminate nuisance trips $5,059 $4,000 $613
26,253
kWh
$4,446
-
kW-mo/yr
-
04 2.6242: Minimize operation of equipment maintained in standby condition $3,047 $2,600 $3,047
130,500
kWh
- -
05 2.2511: Insulate bare equipment $309 $723 $223
9,534
kWh
$86
-
kW-mo/yr
-
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,853 - - $2,853
-
kW-mo/yr
-
07 2.8114: Change rate schedules or other changes in utility service $4,897 $200 - - $4,897
TOTAL RECOMMENDED $25,062 $25,523 $3,328
142,526
kWh
$16,837
-
kW-mo/yr
$4,897
TOTAL IMPLEMENTED $13,158 $17,400 $(-29.0)
(-1,249)
kWh
$8,290
-
kW-mo/yr
$4,897
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs