ITAC Assessment: UU0261
ITAC logo
ITAC Assessment: UU0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Aerospace Engineering and Manufacturing
NAICS 336411: Aircraft Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 186
Plant Area 135,000
ft2
Annual Production 840
units
Production Hrs. Annual 4,700
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,499 1,740,600
kWh
Electricity Demand $89,423 5,504
kW-mo/yr
Electricity Fees $30,539 -
Natural Gas $46,454 3,718
MMBtu
TOTAL YEARLY COSTS $228,915
RECOMMENDED SAVINGS* $40,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $22,296 $572,100 $17,558
489,000
kWh
$4,738
-
kW-mo/yr
-
02 2.7232: Replace existing hvac unit with high efficiency model $2,592 $37,200 $2,417
67,300
kWh
$175
-
kW-mo/yr
-
03 4.211: Consider use / purchase of bulk materials where possible $12,100 $21,600 - - $12,100
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,063 $9,140 $952
26,500
kWh
$1,111
-
kW-mo/yr
-
05 2.4239: Eliminate or reduce compressed air usage $1,386 $8,280 $255
7,100
kWh
$1,131
-
kW-mo/yr
-
06 2.4322: Use or replace with energy efficient substitutes $400 $5,940 $205
5,700
kWh
$195
-
kW-mo/yr
-
TOTAL RECOMMENDED $40,837 $654,260 $21,387
595,600
kWh
$7,350
-
kW-mo/yr
$12,100
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs