Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

54

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Other motor vehicle parts manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
WM0259 #05 Y:2026 Install spectral reflectors / delamp $265 -
WM0259 #04 Y:2026 Install adequate dryers on air lines to eliminate blowdown $1,514 $1,508
WM0259 #03 Y:2026 Use waste heat from hot flue gases to preheat incoming fluids $24,491 $20,000
WM0259 #02 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $46,427 $10,000
WM0259 #01 Y:2026 Reschedule plant operations or reduce load to avoid peaks $134,432 -
WM0033 #08 Y:2013 Begin a practice of predictive / preventative maintenance $5,500 $1,860
WM0033 #07 Y:2013 Conserve energy by efficient use of vending machines $204 $273
WM0033 #06 Y:2013 Install compressor air intakes in coolest locations $3,383 $3,066
WM0033 #05 Y:2013 Install occupancy sensors $93 $315
WM0033 #04 Y:2013 Lease / purchase baler; sell cardboard to recycler $4,441 $5,000
WM0033 #03 Y:2013 Lower temperature during the winter season and vice-versa $617 -
WM0033 #02 Y:2013 Reschedule plant operations or reduce load to avoid peaks $2,046 -
WM0033 #01 Y:2013 Improve air circulation with destratification fans / other methods $24,320 $57,920
WM0008 #10 Y:2012 Use proper thickness of insulation on building envelope $840 $400
WM0008 #09 Y:2012 Use proper thickness of insulation on building envelope $9,137 $3,034
WM0008 #08 Y:2012 Install occupancy sensors $1,209 $990
WM0008 #07 Y:2012 Turn off equipment when not in use $432 $520
WM0008 #06 Y:2012 Turn off equipment when not in use $2,737 -
WM0008 #05 Y:2012 Install compressor air intakes in coolest locations $3,551 $1,000
WM0008 #04 Y:2012 Cool compressor air intake with heat exchanger $40,676 $83,400