Assessment Year | 2013 |
---|---|
Principal Product | Heavy Metal Fabrication |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 275 |
Plant Area |
212,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,375 | 3,912,062 |
kWh
|
$0.055 |
Electricity Demand | $108,941 | 13,706 |
kW-mo/yr
|
$7.95 |
Electricity Fees | $33,435 | - |
|
- |
Natural Gas | $164,550 | 35,087 |
MMBtu
|
$4.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,604 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,534 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $24,320 | $57,920 | - | - |
$24,320
-
MMBtu
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,046 | - | - |
$2,046
-
kW-mo/yr
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $617 | - |
$434
6,921
kWh
|
$183
-
kW-mo/yr
|
- | - | |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,441 | $5,000 | - | - | - | $4,441 | |
05 | 2.7135: Install occupancy sensors | $93 | $315 |
$93
1,486
kWh
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $3,383 | $3,066 |
$2,465
39,288
kWh
|
$918
-
kW-mo/yr
|
- | - | |
07 | 2.6211: Conserve energy by efficient use of vending machines | $204 | $273 |
$204
3,257
kWh
|
- | - | - | |
08 | 4.611: Begin a practice of predictive / preventative maintenance | $5,500 | $1,860 | - | - | - | $5,500 | |
TOTAL RECOMMENDED | $40,604 | $68,434 |
$3,196
50,952
kWh
|
$3,147
-
kW-mo/yr
|
$24,320
-
MMBtu
|
$9,941 | ||
TOTAL IMPLEMENTED | $4,534 | $5,315 |
$93
1,486
kWh
|
- | - | $4,441 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs