| Assessment Year | 2026 |
|---|---|
| Principal Product | Heat Exchangers |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $500 k to 1M |
| # of Employees | 450 |
| Plant Area |
500,000
ft2
|
| Annual Production | 20,000
units
|
| Production Hrs. Annual | 2,100
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $857,327 | 11,848,279 |
kWh
|
$0.072 | |
| Electricity Demand | $670,884 | 36,600 |
kW-mo/yr
|
$18.33 | |
| Electricity Fees | $82,526 | - |
|
- | |
| Natural Gas | $316,875 | 58,267 |
MMBtu
|
$5.44 | |
| Waste Disposal Costs | |||||
| Water Usage | $90,654 | 5,727 |
Tgal
|
$15.83 | |
| TOTAL YEARLY COSTS | $2,018,266 | ||||
| RECOMMENDED SAVINGS* | $207,129 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $134,432 | - | - |
$134,432
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $46,427 | $10,000 |
$34,423
478,094
kWh
|
$12,005
-
kW-mo/yr
|
- | |
| 03 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $24,491 | $20,000 | - | - |
$24,491
-
MMBtu
|
|
| 04 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,514 | $1,508 |
$1,136
15,782
kWh
|
$378
-
kW-mo/yr
|
- | |
| 05 | 2.7144: Install spectral reflectors / delamp | $265 | - |
$151
2,097
kWh
|
$114
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $207,129 | $31,508 |
$35,710
495,973
kWh
|
$146,928
-
kW-mo/yr
|
$24,491
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs