86
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| WI0517 #02 Y:2006 | 02 | 2006 | Reduce hot water temperature to the minimum required | $25,159 | $4,500 | |
| WI0517 #01 Y:2006 | 01 | 2006 | Reschedule plant operations or reduce load to avoid peaks | $27,918 | $6,000 | |
| WI0489 #10 Y:2004 | 10 | 2004 | Turn off equipment when not in use | $206 | - | |
| WI0489 #09 Y:2004 | 09 | 2004 | Install occupancy sensors | $481 | $100 | |
| WI0489 #08 Y:2004 | 08 | 2004 | Maintain air filters by cleaning or replacement | $815 | - | |
| WI0489 #07 Y:2004 | 07 | 2004 | Improve lubrication practices | $735 | $828 | |
| WI0489 #06 Y:2004 | 06 | 2004 | Reduce the pressure of compressed air to the minimum required | $782 | - | |
| WI0489 #05 Y:2004 | 05 | 2004 | Eliminate or reduce compressed air usage | $1,494 | $2,314 | |
| WI0489 #04 Y:2004 | 04 | 2004 | Modify refrigeration system to operate at a lower pressure | $3,606 | $3,000 | |
| WI0489 #03 Y:2004 | 03 | 2004 | Utilize energy-efficient belts and other improved mechanisms | $4,677 | $758 | |
| WI0489 #02 Y:2004 | 02 | 2004 | Use a less expensive method of waste removal | $6,360 | - | |
| WI0489 #01 Y:2004 | 01 | 2004 | Install timers and/or thermostats | $8,655 | $1,600 | |
| WI0462 #08 Y:2003 | 08 | 2003 | Utilize energy-efficient belts and other improved mechanisms | $369 | $438 | |
| WI0462 #07 Y:2003 | 07 | 2003 | Install compressor air intakes in coolest locations | $798 | $840 | |
| WI0462 #06 Y:2003 | 06 | 2003 | Upgrade controls on compressors | $808 | $2,500 | |
| WI0462 #05 Y:2003 | 05 | 2003 | Analyze flue gas for proper air/fuel ratio | $2,319 | $500 | |
| WI0462 #04 Y:2003 | 04 | 2003 | Recharge batteries on during off-peak demand periods | $4,136 | $1,800 | |
| WI0462 #03 Y:2003 | 03 | 2003 | Reschedule plant operations or reduce load to avoid peaks | $3,916 | $8,000 | |
| WI0462 #02 Y:2003 | 02 | 2003 | Replace hydraulic / pneumatic equipment with electric equipment | $8,389 | $14,000 | |
| WI0462 #01 Y:2003 | 01 | 2003 | Use closed cycle process to minimize waste water production | $30,420 | $36,000 |