Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

345

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Printed circuit assembly (electronic assembly) manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MI0294 #01 Y:2016 Lower ceiling to reduce conditioned space $48,743 $88,928
MI0283 #09 Y:2015 Install occupancy sensors $684 $177
MI0283 #08 Y:2015 Install compressor air intakes in coolest locations $688 $639
MI0283 #07 Y:2015 Reduce the pressure of compressed air to the minimum required $942 $40
MI0283 #06 Y:2015 Reduce illumination to minimum necessary levels $2,494 $1,400
MI0283 #05 Y:2015 Utilize higher efficiency lamps and/or ballasts $5,483 $9,820
MI0283 #04 Y:2015 Eliminate leaks in inert gas and compressed air lines/ valves $18,361 $1,660
MI0283 #03 Y:2015 Lower temperature during the winter season and vice-versa $20,030 $160
MI0283 #02 Y:2015 Lower ceiling to reduce conditioned space $54,079 $166,590
MI0283 #01 Y:2015 Utilize a less expensive cooling method $75,489 $140,000
SD0514 #05 Y:2015 Reduce the pressure of compressed air to the minimum required $2,336 $400
SD0514 #04 Y:2015 Install occupancy sensors $2,376 $3,380
SD0514 #03 Y:2015 Eliminate leaks in inert gas and compressed air lines/ valves $2,935 $2,000
SD0514 #02 Y:2015 Reduce temperature of process equipment when on standby $34,024 $1,200
SD0514 #01 Y:2015 Replace electrically-operated equipment with fossil fuel equipment $188,380 $121,434
BD0453 #11 Y:2014 Lease / purchase baler; sell cardboard to recycler $5,040 $6,500
BD0453 #10 Y:2014 Recharge batteries on during off-peak demand periods $160 $20
BD0453 #09 Y:2014 Install occupancy sensors $349 $375
BD0453 #08 Y:2014 Utilize higher efficiency lamps and/or ballasts $447 $470
BD0453 #07 Y:2014 Install compressor air intakes in coolest locations $585 $250