1,818
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UD1100 #08 Y:2024 | 08 | 2024 | Utilize higher efficiency lamps and/or ballasts | $5,007 | $15,430 |
n/a
|
UD1100 #07 Y:2024 | 07 | 2024 | Install occupancy sensors | $5,242 | $7,768 |
n/a
|
UD1100 #06 Y:2024 | 06 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $3,587 | - |
n/a
|
UD1100 #05 Y:2024 | 05 | 2024 | Optimize plant power factor | $12,387 | $23,400 |
n/a
|
UD1100 #04 Y:2024 | 04 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,770 | $1,235 |
n/a
|
UD1100 #03 Y:2024 | 03 | 2024 | Reduce space conditioning during non-working hours | $879 | - |
n/a
|
UD1100 #02 Y:2024 | 02 | 2024 | Keep doors and windows shut when not on use | $1,520 | $1,237 |
n/a
|
UD1100 #01 Y:2024 | 01 | 2024 | Utilize energy-efficient belts and other improved mechanisms | $118 | - |
n/a
|
LE0587 #07 Y:2024 | 07 | 2024 | Utilize higher efficiency lamps and/or ballasts | $735 | $2,997 |
n/a
|
LE0587 #06 Y:2024 | 06 | 2024 | Preheat combustion air with waste heat | $4,080 | $15,000 |
n/a
|
LE0587 #05 Y:2024 | 05 | 2024 | Replace existing hvac unit with high efficiency model | $1,851 | $6,801 |
n/a
|
LE0587 #04 Y:2024 | 04 | 2024 | Install compressor air intakes in coolest locations | $667 | $2,000 |
n/a
|
LE0587 #03 Y:2024 | 03 | 2024 | Use solar heat to make electricty | $58,495 | $104,135 |
n/a
|
LE0587 #02 Y:2024 | 02 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $10,795 | $1,400 |
n/a
|
LE0587 #01 Y:2024 | 01 | 2024 | Reduce the pressure of compressed air to the minimum required | $2,438 | - |
n/a
|
UU0263 #12 Y:2024 | 12 | 2024 | Replace fossil fuel equipment with electrical equipment | $32,910 | $158,576 |
n/a
|
UU0263 #11 Y:2024 | 11 | 2024 | Apply for tax-free status for energy purchases | $8,090 | $5,000 |
n/a
|
UU0263 #10 Y:2024 | 10 | 2024 | Pay utility bills on time | $1,860 | $1,500 |
n/a
|
UU0263 #09 Y:2024 | 09 | 2024 | Optimize plant power factor | $3,940 | $9,000 |
n/a
|
UU0263 #08 Y:2024 | 08 | 2024 | Use adjustable frequency drive or multiple speed motors on existing system | $945 | $3,580 |
n/a
|