Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

678

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Machine shops
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
NT0043 #05 Y:2025 Optimize plant power factor $17,336 $25,437
NT0043 #04 Y:2025 Replace existing hvac unit with high efficiency model $146,777 $515,060
NT0043 #03 Y:2025 Reduce the pressure of compressed air to the minimum required $4,389 -
NT0043 #02 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $11,473 $5,609
NT0043 #01 Y:2025 Utilize higher efficiency lamps and/or ballasts $9,674 $31,572
LE0595 #07 Y:2024 Replace existing hvac unit with high efficiency model $7,474 $33,700
LE0595 #06 Y:2024 Use / purchase optimum sized compressor $6,157 $20,008
LE0595 #05 Y:2024 Utilize higher efficiency lamps and/or ballasts $79 $185
LE0595 #04 Y:2024 Install occupancy sensors $268 $592
LE0595 #03 Y:2024 Re-use or recycle hot or cold process exhaust air $3,049 $2,500
LE0595 #02 Y:2024 Install timers and/or thermostats $5,954 $1,280
LE0595 #01 Y:2024 Reduce the pressure of compressed air to the minimum required $1,948 -
LS2508 #08 Y:2024 Replace fossil fuel equipment with electrical equipment $8,663 $48,183
LS2508 #07 Y:2024 Use / purchase optimum sized compressor $3,709 $16,949
LS2508 #06 Y:2024 Use most efficient type of electric motors $2,510 $10,600
LS2508 #05 Y:2024 Use solar heat to make electricty $39,572 $160,992
LS2508 #04 Y:2024 Replace existing hvac unit with high efficiency model $1,488 $5,190
LS2508 #03 Y:2024 Eliminate old stock and modify inventory control $9,000 $25,000
LS2508 #02 Y:2024 Install sub-metering equipment $3,313 $3,000
LS2508 #01 Y:2024 Utilize higher efficiency lamps and/or ballasts $771 $675