343
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | Other fabricated wire product manufacturing | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OK1165 #06 Y:2025 | 06 | 2025 | Replace fossil fuel equipment with electrical equipment | $20,220 | $86,500 |
n/a
|
| OK1165 #05 Y:2025 | 05 | 2025 | Utilize higher efficiency lamps and/or ballasts | $1,312 | $7,084 |
n/a
|
| OK1165 #04 Y:2025 | 04 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $25,293 | $40,074 |
n/a
|
| OK1165 #03 Y:2025 | 03 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $9,988 | $13,005 |
n/a
|
| OK1165 #02 Y:2025 | 02 | 2025 | Use computer programs to optimize hvac performance | $2,462 | $23,200 |
n/a
|
| OK1165 #01 Y:2025 | 01 | 2025 | Clean and maintain refrigerant condensers and towers | $294 | $935 |
n/a
|
| MI0466 #06 Y:2025 | 06 | 2025 | Utilize higher efficiency lamps and/or ballasts | $1,327 | $3,414 |
n/a
|
| MI0466 #05 Y:2025 | 05 | 2025 | Optimize plant power factor | $8,024 | $18,830 |
n/a
|
| MI0466 #04 Y:2025 | 04 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $4,309 | $4,560 |
n/a
|
| MI0466 #03 Y:2025 | 03 | 2025 | Use solar heat to make electricty | $58,107 | $6,400 |
n/a
|
| MI0466 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $10,332 | $1,020 |
n/a
|
| MI0466 #01 Y:2025 | 01 | 2025 | Change rate schedules or other changes in utility service | $1,368 | $100 |
n/a
|
| WM0235 #04 Y:2024 | 04 | 2024 | Lower temperature during the winter season and vice-versa | $1,413 | - | |
| WM0235 #03 Y:2024 | 03 | 2024 | Reduce space conditioning during non-working hours | $2,882 | - | |
| WM0235 #02 Y:2024 | 02 | 2024 | Install compressor air intakes in coolest locations | $2,895 | $12,010 | |
| WM0235 #01 Y:2024 | 01 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,877 | $3,500 | |
| AM0900 #06 Y:2023 | 06 | 2023 | Recover waste heat from equipment | $29,310 | $69,700 |
n/a
|
| AM0900 #05 Y:2023 | 05 | 2023 | Use synthetic lubricant | $727 | $546 |
n/a
|
| AM0900 #04 Y:2023 | 04 | 2023 | Utilize energy-efficient belts and other improved mechanisms | $1,024 | $546 |
n/a
|
| AM0900 #03 Y:2023 | 03 | 2023 | Reduce the pressure of compressed air to the minimum required | $1,283 | $273 |
n/a
|