ITAC Assessment: AM0900
ITAC logo
ITAC Assessment: AM0900
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Coil springs
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 137
Plant Area 100,000
ft2
Annual Production 468,000
units
Production Hrs. Annual 2,875
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,904 2,767,462
kWh
Electricity Demand $103,106 10,136
kW-mo/yr
Electricity Fees $6,504 -
Natural Gas $177,591 24,733
MMBtu
TOTAL YEARLY COSTS $415,105
RECOMMENDED SAVINGS* $57,406 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,923 $10,333 $5,923
128,773
kWh
- -
02 2.3212: Optimize plant power factor $19,139 $30,070 - $19,139
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,283 $273 $323
7,010
kWh
$960
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,024 $546 $517
11,252
kWh
$507
-
kW-mo/yr
-
05 2.4314: Use synthetic lubricant $727 $546 $367
7,978
kWh
$360
-
kW-mo/yr
-
06 2.2437: Recover waste heat from equipment $29,310 $69,700 - - $29,310
-
MMBtu
TOTAL RECOMMENDED $57,406 $111,468 $7,130
155,013
kWh
$20,966
-
kW-mo/yr
$29,310
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs