Assessment Year | 2024 |
---|---|
Principal Product | Coil springs |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $10 M to 50M |
# of Employees | 137 |
Plant Area |
100,000
ft2
|
Annual Production | 468,000
units
|
Production Hrs. Annual | 2,875
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,904 | 2,767,462 |
kWh
|
$0.046 |
Electricity Demand | $103,106 | 10,136 |
kW-mo/yr
|
$10.17 |
Electricity Fees | $6,504 | - |
|
- |
Natural Gas | $177,591 | 24,733 |
MMBtu
|
$7.18 |
TOTAL YEARLY COSTS | $415,105 | |||
RECOMMENDED SAVINGS* | $57,406 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,923 | $10,333 |
$5,923
128,773
kWh
|
- | - | |
02 | 2.3212: Optimize plant power factor | $19,139 | $30,070 | - |
$19,139
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,283 | $273 |
$323
7,010
kWh
|
$960
-
kW-mo/yr
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,024 | $546 |
$517
11,252
kWh
|
$507
-
kW-mo/yr
|
- | |
05 | 2.4314: Use synthetic lubricant | $727 | $546 |
$367
7,978
kWh
|
$360
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $29,310 | $69,700 | - | - |
$29,310
-
MMBtu
|
|
TOTAL RECOMMENDED | $57,406 | $111,468 |
$7,130
155,013
kWh
|
$20,966
-
kW-mo/yr
|
$29,310
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs