Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

242

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Plate work manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MU0077 #07 Y:2025 Install partitions to reduce size of conditioned space $1,816 $2,353
MU0077 #06 Y:2025 Reduce space conditioning during non-working hours $1,230 -
MU0077 #05 Y:2025 Keep equipment clean $1,593 -
MU0077 #04 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $57 $80
MU0077 #03 Y:2025 Install vinyl strip / high speed / air curtain doors $3,424 $4,121
MU0077 #02 Y:2025 Recover heat from exhausted steam, hot air or hot water $8,641 $62,943
MU0077 #01 Y:2025 Recharge batteries on during off-peak demand periods $13,036 $2,070
WV0685 #07 Y:2025 Reduce the pressure of compressed air to the minimum required $240 $210
WV0685 #06 Y:2025 Eliminate or reduce compressed air usage $366 $435
WV0685 #05 Y:2025 Install outside air damper / economizer on hvac unit $1,728 $8,100
WV0685 #04 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $2,123 $513
WV0685 #03 Y:2025 Reschedule plant operations or reduce load to avoid peaks $3,411 $9,050
WV0685 #02 Y:2025 Install occupancy sensors $7,381 $3,621
WV0685 #01 Y:2025 Utilize higher efficiency lamps and/or ballasts $14,445 $16,580
MS0435 #05 Y:2024 Optimize plant power factor $609 $2,713
MS0435 #04 Y:2024 Change rate schedules or other changes in utility service $3,222 -
MS0435 #03 Y:2024 Replace fossil fuel equipment with electrical equipment $10,911 $100,000
MS0435 #02 Y:2024 Use solar heat to make electricty $101,423 $659,750
MS0435 #01 Y:2024 Install timers on light switches in little used areas $37,679 $1,527
MS0430 #04 Y:2024 Utilize controls to operate equipment only when needed $8,494 -